Multiple Choice
Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.The critical chain does NOT pass through:
A) Activity A.
B) Activity F.
C) Activity E.
D) Activity D.
Correct Answer:

Verified
Correct Answer:
Verified