Multiple Choice
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?
A) $20,000 per week
B) $33,333 per week
C) $5,000 per week
D) $13,333 per week
Correct Answer:

Verified
Correct Answer:
Verified
Q26: A basic Gantt chart:<br>A)clearly displays early and
Q27: Networks would not be well suited for:<br>A)planning
Q28: Activities A and B have a finish
Q29: A(n)_ relationship is appropriate where two or
Q30: If an activity's cost is plotted against
Q32: In analyzing crash options for project activities,each
Q34: Which statement about this Gantt chart is
Q35: Use the Gantt chart and activity list
Q36: When involved in a project involving many
Q43: Sketch a network and use it as