An Activity Performed by a Subcontractor Is Scheduled for 20

Question 31

Multiple Choice

An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?


A) $20,000 per week
B) $33,333 per week
C) $5,000 per week
D) $13,333 per week