Multiple Choice
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?
A) $0 per week
B) $1,000 per week
C) $2,000 per week
D) $6,000 per week
Correct Answer:

Verified
Correct Answer:
Verified
Q50: Dummy activities are used in AOA networks
Q81: Which of the activities in the diagram
Q83: The AOA network described by this table
Q84: The three principal methods for accelerating project
Q85: An AOA network:<br>A)cannot show a merge activity.<br>B)cannot
Q87: A project has the activity duration and
Q88: Use the Gantt chart and activity list
Q89: The AOA network described by this table
Q90: AON networks have an advantage over AOA
Q91: The process of accelerating a project is