Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 69

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project? A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?   A) $222,667 B) $217,000 C) $222,000 D) $208,000


A) $222,667
B) $217,000
C) $222,000
D) $208,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions