Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?
A) $222,667
B) $217,000
C) $222,000
D) $208,000
Correct Answer:

Verified
Correct Answer:
Verified