True/False
Fixed overhead does not have separate price and quantity variances.The model used to analyze variable costs does not apply to fixed overhead,so the fixed overhead spending variance cannot be broken down into price and quantity variances.
Correct Answer:

Verified
Correct Answer:
Verified