menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Managerial Accounting Study Set 17
  4. Exam
    Exam 4: Activity-Based Costing and Cost Management
  5. Question
    Under Activity Based Management,cost Management Is Achieved by
Solved

Under Activity Based Management,cost Management Is Achieved by

Question 76

Question 76

Multiple Choice

Under activity based management,cost management is achieved by


A) Managing the underlying activities.
B) Reducing production volume.
C) Eliminating value-added activities.
D) Assigning indirect costs to products based on their activities.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: Sherman,Inc.manufactures chainsaws that sell for $58.Each chainsaw

Q16: Pima,Inc.manufactures calculators that sell for $40 each.Each

Q27: Garfield Personal Training Services is owned by

Q65: Which of the following best defines a

Q66: An activity that is performed to support

Q75: Activity-based costing is not appropriate for service

Q78: In a traditional volume-based cost system,total manufacturing

Q80: A value-added activity is one that enhances

Q81: The first step in ABC is to

Q98: An activity that is performed for a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines