Approximately What Percent of the Project Time Line Should Be

Question 4

Short Answer

Approximately what percent of the project time line should be devoted to each of the activities listed below?
Planning ______
Analysis ______
Design ______
Coding ______
Testing ______
If you could expend more time in one activity,which would have the highest likelihood of improving software quality? Why?

Correct Answer:

verifed

Verified

Planning 2-3%
Analysis 10-25%
...