Raul was leading a team charged with developing a new system for budgeting.Which of the following questions is best paired with the most appropriate phase of the systems development life cycle?
A) Initiation/planning: Do we really need a new budgeting system?
B) Requirements analysis: Do we really need a new budgeting system?
C) Design: How many people should be on the team?
D) Operations and maintenance: How many people should be on the team?