Multiple Choice
A job was budgeted to require 3 hours of labor per unit at $8.00 per hour.The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000.What is the total labor cost variance?
A) $2,000 unfavorable.
B) $3,000 unfavorable.
C) $6,000 unfavorable.
D) $8,000 unfavorable.
E) $9,000 unfavorablE.
Correct Answer:

Verified
Correct Answer:
Verified