Multiple Choice
Cavern Company's output for the current period results in a $5,250 unfavorable direct material price variance.The actual price per pound is $56.50 and the standard price per pound is $55.00.How many pounds of material are used in the current period?
A) 5,393.
B) 5,110.
C) 3,500.
D) 3,750.
E) 4,000.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Standard costs are used in the calculation
Q35: Lavoie Company planned to use 18,500 pounds
Q109: Use the following data to find the
Q111: A company provided the following direct materials
Q112: In preparing flexible budgets,the costs that remain
Q113: Milltown Company specializes in selling used cars.During
Q114: Standard material costs, standard labor costs, and
Q115: Sanchez Company's output for the current period
Q117: If ending variances account balances are material,they
Q118: Parallel Enterprises has collected the following data