Multiple Choice
Assume that the expectations on the static budget were met.We can conclude that
A) the static budget was ill conceived.
B) the effectiveness of the manager is not in question.
C) the manager is very efficient.
D) there is no need for a flexible budget.
E) none of these.
Correct Answer:

Verified
Correct Answer:
Verified