Multiple Choice
Figure 10-6. Extreme Builders constructs houses.The standard labor rate is $25 per hour and the standard number of hours is 15,000 hours per home.During the year,it constructed 12 homes using 18,000 labor hours per home and a rate of $28 per hour.
Refer to Figure 10-6.Calculate the labor efficiency variance.
A) $1,008,000 F
B) $900,000 U
C) $1,008,000 U
D) $900,000 F
Correct Answer:

Verified
Correct Answer:
Verified