Multiple Choice
Ritchie Company Ritchie Company uses a standard cost system for its production process.Ritchie Company applies overhead based on direct labor hours.The following information is available for July: Refer to Ritchie Company Using the three-variance approach,what is the spending variance?
A) $23,850 U
B) $23,850 F
C) $14,280 F
D) $14,280 U
Correct Answer:

Verified
Correct Answer:
Verified