Multiple Choice
Which of the following are not MRP Design Decisions?
1) time bucket size
2) delivery lead time
3) safety stock size
4) lot-sizing method
A) (1) and (4)
B) (2)
C) (3) and (4)
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified