The push system measures the performance of each work station separately based on measures such as machine utilization.If all the work stations are operating at the peak of their current possible machine utilization, is this enough to say that this push manufacturing process is at an optimal state? Is there areas that could go wrong?

Correct Answer:

verifed

Verified

basic underlining un...