Solved

Dave Is Conducting Rough-Cut Capacity Planning (RCCP)for a Product ATOR

Question 5

Essay

Dave is conducting Rough-Cut Capacity Planning (RCCP)for a product ATOR.The product ATOR' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A, B and C.The Production Routings for product GTB is presented below.Using RCCR approach, find whether Work center 2 has enough capacity to produce 104 units of product ATOR.Work center 2's assigned capacity is 1,100 hours.
Dave is conducting Rough-Cut Capacity Planning (RCCP)for a product ATOR.The product ATOR' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A, B and C.The Production Routings for product GTB is presented below.Using RCCR approach, find whether Work center 2 has enough capacity to produce 104 units of product ATOR.Work center 2's assigned capacity is 1,100 hours.

Correct Answer:

verifed

Verified

No, the required hou...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions