Multiple Choice
Which type of planning tool shows each task as a horizontal bar whose length is proportional to the time required to complete it?
A) PERT chart
B) Gantt chart
C) Both a PERT chart and a Gannt chart
D) Scoring model
E) Portfolio analysis
Correct Answer: