Acceptance testing:
A) includes all the preparations for the series of tests to be performed on the system.
B) tests the functioning of the system as a whole.
C) tests each program separately in the system.
D) provides the final certification that the system is ready to be used in a production setting.
E) tests the conversion of legacy data to the new system.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: In a parallel conversion strategy,the new system:<br>A)is
Q4: A bank has reworked its mortgage application
Q5: A prototype is a working version of
Q6: The idea that the achievement of quality
Q7: Which of the following may occur when
Q9: In object-oriented development:<br>A)the class is used as
Q10: Transferring data from a legacy system to
Q11: CASE tools facilitate the creation of clear
Q12: Object-oriented development could potentially reduce the time
Q13: Briefly describe the four main conversion strategies