Which of the following statements is TRUE about velocity?
A) The customer sets the velocity of each scrum period.
B) When a project begins, the senior team members guess the velocity of the team.
C) After a scrum team commits to requirements in a scrum period, it estimates the velocity it can achieve.
D) A team approaches the scrum master to change the order of the requirements to which it has committed.