Multiple Choice
Genesis Company Genesis Company uses a standard cost system for its production process and applies overhead based on direct labor hours. The following information is available for September when Genesis produced 5,000 units: Refer to Genesis Company. Using the four-variance approach, what is the variable overhead spending variance?
A) $2,525U
B) $4,075 F
C) $4,075 U
D) $4,325 U
Correct Answer:

Verified
Correct Answer: