Multiple Choice
Foundation Construction Company agrees to lay a foundation for Garth, but fails to finish the job. Garth hires Housing Projects Inc. to complete the work. In a suit for breach, Garth may recover from Foundation
A) nothing.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.
Correct Answer:

Verified
Correct Answer:
Verified