Multiple Choice
On January 10th, JON, Inc. enters into a contract in which Jon, Inc. is to deliver 1000 special order widgets to the JPK Construction Company for use in a unique project. Delivery is scheduled for November 23rd. On February 14th, JON, Inc. hears through the grapevine that JPK has entered into a contract with another company to buy the widgets at a lower price. JON, Inc. calls JPK on March 15th and is reassured that the contract will be honored. On August 8th, JPK takes delivery of the widgets from the other company and begins using them in the unique project they are working on. On November 23rd, JON, Inc's truck arrives at JPK's loading dock with the 1000 widgets and JPK refuses to take delivery.
If JON, Inc. wanted damages for the breach of contract but wishes to pursue recovery through ADR rather than litigation but wanted to keep litigation options open, which form of ADR should JON, Inc. avoid?
A) negotiation
B) mediation
C) arbitration
D) mini-trial
E) fact-finding
Correct Answer:

Verified
Correct Answer:
Verified
Q109: In a civil case,which of the following
Q110: For their rulings to be valid,arbitrators must
Q111: Pursuant to the 5th Amendment to the
Q112: The U.S.Congress enacted the Federal Arbitration Act
Q113: An administrative law judge's decision is published
Q115: If the discovery process results in learning
Q116: Mike and Kathy have been dating for
Q117: Information given by the attorneys in their
Q118: Since the plaintiff has the burden of
Q119: A rebuttal is called to counter the