True/False
Josh is having a house built and the contract specifies that the completion date is November 23rd.If the builder doesn't complete the house until November 28th,the builder is not liable for damages unless a "time is of the essence" clause is part of the contractual conditions.
Correct Answer:

Verified
Correct Answer:
Verified