    In Order for a Liquidated Damages Clause in a Contract
Solved

In Order for a Liquidated Damages Clause in a Contract

Question 21

Question 21

True/False

In order for a liquidated damages clause in a contract to be upheld,the actual damages must be difficult or impracticable to determine.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: Where there is an anticipatory repudiation,the non-breaching

Q17: The tort of intentional interference with contractual

Q18: Most contracts are discharged by the complete

Q19: An enforceable liquidated damages clause is a

Q20: An employee whose employer breaches an employment

Q22: Alice has a contract with a surgeon

Q23: Tender of performance is another term for

Q24: A contract that has been fully performed

Q25: Rescission is available for a contract involving

Q26: Several types of monetary damages are recoverable

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines