Multiple Choice
Pat Painter contracts to paint Harry Homeowner's home for $6,000.Pat would supply all materials at a cost to Pat of $1,000.Harry breaches by refusing to let Pat paint the house,which Pat found out before spending any money on the materials.Pat is able to find another job that nets a profit of $4,200 during that same time that Harry's house was to be painted.How much can Pat recover from Harry in damages?
A) $0
B) $800
C) $1,800
D) $3,200
E) $5,000
Correct Answer: