Multiple Choice
In the general model,an efficiency variance is calculated as
A) (SP AQ) - (SP SQ)
B) (AP SQ) - (SP SQ)
C) (AP AQ) - (SP SQ)
D) (AP AQ) - (SP AQ)
Correct Answer:

Verified
Correct Answer:
Verified