One of the Events on the Critical Path for Producing

Question 11

Multiple Choice

One of the events on the critical path for producing a textbook is editing the manuscript. This means that if there is a delay in the editing process, which of the following will result?


A) more resources devoted to those events not on the critical path
B) no other events taking place until the delay is over
C) a delay in the completion of the project as a whole
D) a delay in the launch of the production process