Multiple Choice
An assembly line has 10 stations with process times of 1, 2, 3, 4, …, 10 respectively. The process time of the system is
A) 18.18% of the process cycle time.
B) 100% of the process cycle time.
C) 550% of the process cycle time.
D) 50% of the process cycle time.
E) 2% of the process cycle time.
Correct Answer: