Which of the following is not an element of the disaster risk decision tree model?
A) the buyer's financial loss incurred in a supply cycle if supplier i were disrupted
B) the marginal cost of managing a supplier
C) the buyer's financial loss incurred in a supply cycle if all suppliers were disrupted
D) the probability of a "super-event" that would disrupt all suppliers simultaneously
E) the probability of a "unique-event" that would disrupt only one supplier
Correct Answer: