The second unit of production took 9 hours. If the learning curve is 90% how long did the first unit take?


A) 9 hours
B) 10 hours
C) 8.1 hours
D) 8.5 hours
E) 8.8 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: The fact that human activities typically improve

Q68: The arithmetic approach (or successive doubling approach)

Q108: The first unit of a product took

Q109: Learning curves can be applied to a

Q110: The learning curve for a product is

Q111: The first unit took 10 hours and

Q114: Which one of the following statements about

Q115: If it took 1000 hours to produce

Q116: To use the table of learning curve

Q117: Which of the following statements comparing learning

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines