A Company Negotiates a Price for Two Aircraft That Includes

Question 103

Multiple Choice

A company negotiates a price for two aircraft that includes a reduction in labour on the second aircraft consistent with a 70% learning curve. Suppose the first aircraft took 100 hours. If the improvement rate changes to 20%, how will the total time to complete both aircraft change?


A) no change
B) -10 hours
C) + 10 hours
D) -50 hours
E) + 50 hours