A product was priced assuming an 80% learning rate. How much extra labour (in $) will be required on the 4th product if the learning rate is actually 90%? Assume that labour costs $10/hour and the first unit cost $100 to produce.
Correct Answer:

Verified
4-.322 = .64 and 4-.152 = .81