Essay
A manufacturing plant is trying to determine how long the average line for a repair process will be. If 10 machines arrive each hour and must wait 7 minutes in the line, how long will the line be, on average?
Correct Answer:

Verified
Little's Law X machines = 10 m...View Answer
Unlock this answer now