A manager must decide on the mix of products to produce for the coming week. Product A requires three minutes per unit for molding, two minutes per unit for painting, and one minute for packing. Product B requires two minutes per unit for molding, four minutes for painting, and three minutes per unit for packing. There will be 600 minutes available for molding, 600 minutes for painting, and 420 minutes for packing. Both products have contributions of $1.50 per unit. Answer the following questions; base your work on the solution panel provided.
a. What combination of A and B will maximize contribution?
b. What is the maximum possible contribution?
c. Are any resources not fully used up? Explain.
Correct Answer:

Verified
Maximum contribution occurs at A = 150, ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q11: The graphical method of solving linear programming
Q16: The optimal solution to a linear programming
Q23: The Queen City Nursery manufactures bags of
Q29: A common form of the product-mix linear
Q33: In a linear programming problem, what is
Q61: Which of the following is not a
Q93: A financial advisor is about to build
Q94: A maximizing linear programming problem with constraints
Q96: Suppose that a maximization LP problem has
Q97: The feasible region in the diagram below