Essay
Cyclone Appliances has developed a new European-style convection oven that will be made on an assembly line. The schedule requires 80 ovens in an 8-hour day. The assembly includes seven tasks. The table below indicates the performance time and the sequence requirements for each task.
a. What is the cycle time for this assembly operation?
b. What is the theoretical minimum number of workstations?
c. Draw the precedence diagram.
Correct Answer:

Verified
(a) The cycle time is 480 minutes per da...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q33: A production line is to be designed
Q34: A manufacturing work cell has a takt
Q37: A disadvantage of product-oriented layout is that<br>A)
Q86: The major problem addressed by the process-oriented
Q109: Which layout type assumes an adequate volume
Q126: Cycle time is the maximum time that
Q144: CRAFT is software for balancing assembly lines.
Q156: A focused work center is well suited
Q159: In the Office Relationship Chart, which rating
Q254: A production line is to be designed