Multiple Choice
Which of the following statements regarding Gantt charts is true?
A) Gantt charts give a timeline and precedence relationships for each activity of a project.
B) Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery.
C) Gantt charts are visual devices that show the duration of activities in a project.
D) Gantt charts are expensive.
E) Gantt charts identify the critical path.
Correct Answer:

Verified
Correct Answer:
Verified