Multiple Choice
A project being analyzed by PERT has 50 activities, 12 of which are on the critical path. If the estimated time along the critical path is 176 days with a project variance of 144, the probability that the project will take 194 days or more to complete is
A) near zero.
B) 0.0126.
C) 0.0668.
D) 0.9332.
E) 2.00.
Correct Answer: