    Describe in Words How to Calculate a Project's Standard Deviation
Solved

Describe in Words How to Calculate a Project's Standard Deviation

Question 56

Question 56

Essay

Describe in words how to calculate a project's standard deviation. What assumption allows that calculation to be accurate?

Correct Answer:

verifed

Verified

Add the variances of the activ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q51: The shortest of all paths through the

Q52: The difference between AON and AOA networks

Q53: Define slack time.

Q54: The _ distribution is appropriate for calculating

Q55: Ethical issues that can arise in projects

Q57: The expected activity time in PERT analysis

Q58: A project being analyzed by PERT has

Q59: Which of the following projects was NOT

Q60: The network below represents a project being

Q61: Identify several advantages of using PERT (and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines