Essay
The network below represents a project being analyzed by Critical Path Methods. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6. a. What task must be on the critical path, regardless of activity durations?
b. What is the duration of path A-B-E-H-J?
c. What is the critical path of this network?
d. What is the length of the critical path?
e. What is slack time at activity H?
f. What is the Late Finish of activity H?
g. If activity C were delayed by two time units, what would happen to the project duration?
Correct Answer:

Verified
(a) J; (b) 20; (c) A...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q30: What are the three phases of a
Q31: A simple CPM network has three activities,A,B,and
Q35: What is the basic difference between PERT
Q40: Explain why the critical path is the
Q60: WBS stands for which of the following
Q61: Which of the following statements regarding CPM
Q63: An activity on a PERT network has
Q64: Which of these statements regarding time-cost tradeoffs
Q80: A code of ethics especially for project
Q123: A diagram of all activities and the