Solved

Given the Critical Path Below, Calculate the Following
A

Question 121

Essay

Given the critical path below, calculate the following
a. The crash cost per unit time savings for each activity.
b. The maximum total crash time savings and cost.
c. The maximum total time-savings with a $3000 budget.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 8 days $8,0007 days $12,000 B 5 days $2,0003 days $10,000 C 10 days $9,0009 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 8 \text { days } & \$ 8,000 & 7 \text { days } & \$ 12,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 3 \text { days } & \$ 10,000 \\\hline \text { C } & 10 \text { days } & \$ 9,000 & 9 \text { days } & \$ 12,000 \\\hline\end{array}

Correct Answer:

verifed

Verified

(A) A saves 1 day for $4000/day, B saves...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions