Multiple Choice
The short-term scheduling activity called loading
A) assigns dates to specific jobs or operations steps.
B) specifies the order in which jobs should be done at each centre.
C) assigns jobs to work centres.
D) assigns workers to jobs.
E) assigns workers to machines.
Correct Answer:

Verified
Correct Answer:
Verified