Multiple Choice
If an assignment problem consists of 6 workers and 7 projects:
A) one worker will not get a project assignment.
B) one worker will be assigned two projects.
C) each worker will contribute work toward the seventh project.
D) one project will not get a worker assigned.
E) The problem cannot be solved by assignment method.
Correct Answer: