Multiple Choice
Average completion time for a schedule sequence at a work centre is the ratio of
A) total processing time to the number of jobs.
B) total flow time to total processing time.
C) total flow time to the number of jobs.
D) total processing time plus total late time to the number of jobs.
E) total flow time plus total late time to the number of jobs.
Correct Answer:

Verified
Correct Answer:
Verified