Multiple Choice
If a load report (resource requirements profile) shows a work centre scheduled beyond capacity
A) the company must add capacity by enlarging the facility.
B) the company must add capacity by such tactics as overtime and subcontracting.
C) the work centre's load may be smoothed by such tactics as operations splitting or lot splitting.
D) the aggregate plan must be revised.
E) the Wagner-Whitin algorithm should be used to rebalance the load.
Correct Answer:

Verified
Correct Answer:
Verified