Osprey Machine Works has the following demand requirements and other data for the upcoming four quarters.
 Quarter  Demand  Previous quarter’s output 2500 units 12300 Beginning inventory 200 units 22400 Stockout (backorder) cost $50 per unit 32600 Inventory holding cost  $10 per unit at  end of quarter 42100 Hiring workers $4 per unit  Laying off workers  $8 per unit  Unit cost  $30 per unit  Overtime  $10 extra per unit \begin{array}{|l|l|l|l|}\hline\text { Quarter } & \text { Demand } & \text { Previous quarter's output } & 2500 \text { units } \\\hline 1 & 2300 & \text { Beginning inventory } & 200 \text { units } \\\hline 2 & 2400 & \text { Stockout (backorder) cost } & \$ 50 \text { per unit } \\\hline 3 & 2600 & \text { Inventory holding cost } & \text { \$10 per unit at } \\&&&\text { end of quarter }\\\hline4 & 2100 & \text { Hiring workers } & \$ 4 \text { per unit } \\\hline & & \text { Laying off workers } & \text { \$8 per unit } \\\hline & & \text { Unit cost } & \text { \$30 per unit } \\\hline && \text { Overtime } & \text { \$10 extra per unit } \\\hline\end{array} What is the total cost of pursuing a level aggregate plan over the coming year?

Correct Answer:

verifed

Verified

Requirements total 9400 units,...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions