The data below represent time study observations for an assembly operation. Assume a 7% allowance factor. What is the normal time for element 3?
A) 1.7 min.
B) 1.96 min.
C) 2.11 min.
D) 10.1 min.
E) 11.2 min.
Correct Answer:

Verified
Correct Answer:
Verified