Essay
A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.
a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances are 8% constant and 6% variable?
d. If the analyst then thought more carefully about his experiment, and decided that the variable allowances needed to be increased to match the real (outside, unair-conditioned) work environment, and that the proper variable allowance was not 6% but 12%, what is the revised standard time?
Correct Answer:

Verified
Correct Answer:
Verified
Q1: The accuracy of a labour standard is
Q9: List the eight steps used to develop
Q23: A Therblig is a very small amount
Q131: Mutual trust means that both management and
Q148: How do we establish a fair day's
Q149: A bank manager wants to determine the
Q160: The visual workplace<br>A) uses low-cost visual devices
Q172: _ showed that there is a dynamic
Q189: Equitable pay alone cannot achieve a reasonable
Q292: Identify the five components of job design.