Essay
A task involves positioning two metal parts with a rubber gasket sandwiched between them, inserting two bolts into predrilled holes, threading a nut onto each bolt, and tightening each bolt with a pneumatic wrench. In a preliminary study, the manager observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.
a. What is the average observed time for this task?
b. What is the normal time for this task if the employee worked at a 10% slower pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances are 7% constant and 5% variable?
Correct Answer:

Verified
Note that the fourth time must be discar...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q51: Job rotation is an example of<br>A) job
Q52: A brake system installer in an auto
Q85: In a large aerospace company, it has
Q97: What is the required sample size to
Q107: When a worker has a say in
Q190: Labour planning determines employment stability.
Q192: Job expansion can lead to increased labour
Q193: Working 4 shifts of ten hours instead
Q199: A manufacturing plant assembly line job has
Q259: The allowances that convert normal time to