Multiple Choice
If the following jobs are sequenced according to the SPT rule,then the mean tardiness (in days) for all jobs is (assume zero for today's date)
A) 16 days.
B) 13 days.
C) 5.2 days.
D) 3.2 days.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q16: If the following jobs are sequenced according
Q17: What is the difference between infinite scheduling
Q23: The following set of jobs must be
Q26: Input/output control provides the information necessary to
Q46: The scheduling rule that minimizes the makespan
Q66: If a job is ahead of schedule,then
Q79: Typically, there are more options available when
Q79: The sequence in which jobs should be
Q92: Gantt charts show the planned and yet
Q94: Minimizing overtime is one of several objectives