Multiple Choice
A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period. If EOQ lot sizing is used the minimum order quantity would be
A) 85.
B) 100.
C) 120.
D) 150.
Correct Answer:

Verified
Correct Answer:
Verified